Cone crusher is a comm used crushing equipment, and there are two major issues about its installation and operation. Reasonable installation can avoid equipment damage to the machine during the second operation, and can also improve production efficiency. Guarantee, and can extend the life of the machine. Therefore, the installation of the device is critical. , Shanghai SBM expert team will tell you about two precautions in the installation process of cone crusher, and hope to help you.
Cone crusher equipment
Installation requirements for cone crusher

In order to ensure safe operation, we pay attention to the installation of the cone crusher. Before installation, the installer should inspect the equipment to eliminate the two problems that occur during transportation, such as damage or contamination of the equipment parts, and missing, etc., and install according to the following requirements to avoid installation defects.
    (1) The cone crusher should be installed on the concrete foundation.
    (2) In order to avoid the vibration of the cone crusher, a hardwood plate or other damping material should be placed between it and the concrete foundation.
    (3) When installing the cone crusher, ensure that the motor and rotor shaft are flat to avoid affecting the premature damage of the elastic sleeve and the coupling of bearing heating.
Spring Cone Crusher

PY series spring cone crusher
Cone crusher operation
(1) Preparation of cone crusher before driving:

    1. If there are two, check the bearing lubricant.
    Second, check whether all fasteners are fully tightened.
    Third, check whether there is metal or other fragile debris on the device.
    Fourth, check whether the hammer and the crushing cavity are normal.
    5. Rotate the rotor by hand and observe whether it is normal. Regardless of whether the direction of rotation is correct or not, there is no collision between the hammer and other parts.
Cone crusher equipment
(2) Start-up of cone crusher:

    First, after inspection, it is proved that the machine and the transmission part are normal, and we can turn on the machine.
    2. During the operation, if two abnormal situations are found, the operation should be s ped. After eliminating the fault, before restarting the crusher, check again for abnormal conditions.
(3) Precautions when using cone crusher:
    First, after the crusher runs normally, we can do the work of feeding.
    Second, the feed enter the crusher evenly and should be distributed over the length of the rotor's working part to prevent the motor load from increasing suddenly.
    Third, regular inspection, such as plugs should be removed in a timely manner.
    Under normal circumstances, the temperature rise of the bearing should be in the range of 35 ° C, and the relatively high temperature should not exceed 70 ° C. If it exceeds 70 ℃, it should be s ped immediately to determine the reason for cancellation, and then the test machine should be restarted.